Desalination plant

Location: Telde, Gran Canaria. Spain Date: 2008 Client: ACCIONA Area / Length: 3400 m² Global budget: € 708,584 Budget of the tasks undertaken: € 708,584
Tasks undertaken: Basic Engineering, Detail Engineering Technical areas: Structural Engineering Areas of action: Energy and Industry

ACCIONA has been contracted to build a seawater desalinization plant in Telde. ACCIONA has contracted 3D3 INGENIERÍA for the foundations and structural project of the plant and for assistance to worksite tasks.
The project consists of several treatment and water storage tanks, an office building and a water processing warehouse.
From a structural point of view, the warehouse is projected with a steel structure, with three cranes inside that work simultaneously, and several concrete tanks with precast concrete roofs. In addition, there are several hoists hanging from the roof structure.
Office buildings are projected with cast in place concrete structures in columns and beams and precast concrete slabs for frameworks.