Remodeling of the electrical substation ST Argüelles

Location: Madrid. Spain Date: 2011 Client: Iberdrola Ingeniería y Construcción Area / Length: 862 m² Global budget: € 760,000 Budget of the tasks undertaken: € 760,000
Tasks undertaken: Project Review, Recalculation and expert evaluation, Technical site management Technical areas: Structural Engineering, Civil engineering, Rehabilitations, Other Services Areas of action: Energy and Industry

The refurbishment of ST Arguelles consists of several works with the final purpose of updating the building to the new CPI Standards and preparing it for the installation of a new room for a GIS.
Main works are the following:
Demolition of a reinforced concrete slab.
Reinforcement of the existing structure.
Room restoration for the new installation.
All demolition works are done while the substation is in operation and with a fixed deadline because of the arrival of the equipment. Supervision takes place daily, modifying and adapting the project to the works’ requirements, using new drawings and drafts. The works program is also thoroughly controlled by detailing up to 26 different tasks.
Works are done during summer and autumn 2011, complying with the previously set delivery deadlines.